It should be noted right away that in this article we will consider the main stages of technological connection to the power grids of MOESK (Moscow Electric Grids) for consumer citizens and business owners who need a maximum power of up to 15 kW.

In our opinion, in recent years there have been many positive changes in the procedure for connecting to the power grid. This is especially true for residents of the Moscow region and the capital of Russia.

Here we wanted to talk about the introduction of new technologies by MOESK and positive changes in this regard, as well as how they can make life easier for an ordinary person who does not know all the intricacies of the procedure for technological connection to power grids.

Now you can connect to the power grid even without ever going to the power grid.

Any person has the opportunity to apply for technological connection to the power grids of MOESK via the Internet on the official website of the company.

For several years, the portal for technological connections of MOESK http://utp.moesk.ru has been functioning.

It is on this portal that any applicant can register in a personal account and apply for connection to MOESK networks in Moscow or the Moscow Region.

To start the procedure for connecting to the power grids of MOESK with the submission of documents via the Internet, you need to:

1. Register in your personal account on the official website of MOESK (http://utp.moesk.ru).

2. Make scanned copies of the following documents:

  • Passports.
  • Certificate of ownership of the land or an extract from the cadastral passport.
  • SNILS (certificate of pension insurance).

3. If you need to increase the capacity, then you must also copy the documents confirming the available capacity (act of delimitation of balance ownership or act of technological connection).

During 7 days an agreement signed with an electronic digital signature by MOESK on technological connection to power grids and technical specifications should be received in the personal account.

Important: If you need a maximum power of up to 15 kW and the distance in a straight line to the power grids of MOESK does not exceed 300 meters in urban areas and 500 meters in rural areas, then the cost of connecting to power grids will be Your object 550 rubles.

If any of the conditions is not met, then the cost of connecting to MOESK will be a larger amount. This amount is calculated based on the tariffs approved by the committee and according to the tariffs and prices of the Moscow Region (or the Department of Economics of the City of Moscow). The total cost of MOESK services is indicated in the connection agreement.

5. If all the terms of the contract suit you, then you need to confirm your agreement with its terms and cost through the code received in SMS.

6. Let's move on to the main stage - the construction of power grids by MOESKOM (if necessary) and the fulfillment by you of the technical conditions.

MOESK starts construction of power grid facilities up to the boundaries of your site, and you need to fulfill the technical conditions that are provided for in the contract (install a metering cabinet, an electricity meter, and perform electrical work on your site, etc.).

To fulfill the technical conditions, it is better to involve qualified specialists with relevant experience and permits, although this is not a prerequisite - if you have confidence in your abilities, you can do all the work on your site yourself.

The maximum period for which MOESK must complete all work is 180 days from the date of conclusion of the contract (such a period is prescribed in the current legislation).

If there is an already built line near your site, then MOESK connects to its networks almost immediately (within 7-10 days).

If it is necessary to build power grid facilities, then this period will be longer.

7. After fulfilling the technical conditions, you need to inform MOESK about this through your personal account, email or by phone. Specialists will come and accept the fulfillment of technical conditions. If there are no comments, then the voltage is applied on the same day.

8. After some time, documents confirming the proper connection to MOESK will be available to you in your personal account (this is an act of delimitation of the balance ownership of the parties and an act of technological connection).

After that, your object is connected to the power grid!!!

You have just a little bit left to get electricity to your site, house or shop.

For the final settlement of energy supply issues, you also need to conclude an energy supply agreement with Mosenergosbyt (see how to do this here).

By the way, since May 2017 there have been changes in the legislation that allow you to conclude an energy supply agreement immediately upon filing an application for connection to the power grid. To do this, you need to print a standard form of an energy supply contract from the Mosenergosbyt website, sign it, attach copies of the necessary documents and give two copies to MOESK. The power engineers will figure it out on their own.

  • Normative legal acts regulating activities in the field of technological connection.

    • 12.6 MB
    • Rules for the technological connection of power receivers of electric energy consumers, electric energy production facilities, as well as electric grid facilities owned by grid organizations and other persons, to electric networks, approved by Decree of the Government of the Russian Federation No. 861 dated December 27, 2004 2.1 MB
    • Order No. 248-tr dated December 12, 2019 on establishing rates per unit of maximum power at a voltage level below 35 kV and a power below 8900 kW, standardized tariff rates and payment formulas for technological connection to the electric networks of territorial grid organizations in the city of Moscow on 2020 949.2 KB
    • Decree of the Committee for Prices and Tariffs of the Moscow Region dated December 20, 2019 No. 429-R “On the establishment of standardized tariff rates, rates per unit of maximum power and fee formulas for technological connection of power receivers of consumers of electrical energy, power grid facilities owned by grid organizations and other persons , to the electric networks of territorial grid organizations on the territory of the Moscow Region for 2020" 8.0 MB
    • Decree No. 30-R of April 1, 2015 “On Approval of the Regulations of the Committee for Prices and Tariffs of the Moscow Region on Establishing Payments for Grid Organizations for Technological Connection to Electric Grids, Payment Rates per Unit of Capacity and (or) Standardized Tariff Rates that Determine the Value this board" 117.0 KB
    • 1.2 MB
    • 2.6 MB
    • 2.0 MB
    • 300.0 KB
    • 2.0 MB
    • 483.0 KB
    • 198.2 KB
    • 775.8 KB
    • 271.2 KB
    • 7.1 MB
    • 271.7 KB
    • link to third party source
    • Regulations for the provision of services for connecting consumers to electric networks, carried out taking into account the features provided for by the Decree of the Government of the Russian Federation dated August 9, 2017 No. 955 “On establishing the features of the provision of services for connecting (technological connection) to engineering networks in electronic form on territory of the Moscow region and Moscow and St. Petersburg in 2017 - 2021" 531.4 KB

Many citizens of Moscow and the Moscow region, faced with the need to connect objects to external power supply networks, are interested in the procedure for implementing the procedure called - MOESK technological connection . This is due to the fact that the majority of new subscribers in the Moscow region become full-fledged consumers of electricity only after they become customers of the represented company.

The accession sequence is standard, and its passage is similar for almost all new applicants. Therefore, if you do not have a lack of free time, if your element is going through the authorities and boring collection of the necessary documentation, then it is quite possible to perform such a procedure on your own. To do this, visit the company's website, find the section in it - " MOESK official website technological connection» and get acquainted with the features of the provided service. Everything else is in your hands: you can apply on the company's official portal and collect the required documents yourself.

At the same time, the owner of an electrified object always has an alternative: he can turn to the services of specialized specialists or organizations that provide comprehensive support in organizing such work. This will not greatly affect the contents of your wallet, but it will save time and allow you to achieve the final goal without ever visiting the representative office of the electric grid company.

But let's get back to the first way of going through the connection procedure, because today not all potential consumers of electricity are aware of it.

Procedure for submitting an application via the Internet

First of all, the owner of the connected object must register on the website of the network company. Then they are served application for technological connection MOESK. Scanned documents from the following list must be attached to the application:

  • passport scan;
  • a scan of the certificate confirming the right of ownership;
  • an electronic copy of the certificate of compulsory pension insurance.

If electricity supply object implies the simultaneous connection and increase in allocated power, then the applicant is obliged to attach copies of documents confirming the amount of current power. As a rule, these documents are accompanied by acts of delimitation drawn up during the previous connection.

Electronic copies of documents are uploaded to the network company's website, after which the user who submitted the application can count on its consideration in the very near future.

Within the first week from the date of registration of the application, representatives of the power grid organization must provide the applicant with an electronic contract for connecting the facility to the power supply networks. Technical conditions for connecting electricity are provided to the future subscriber together with the contract.

Before starting the connection procedure, the customer must make sure that the connected object is no more than 300 meters away from the centralized networks (for objects located within the city limits) and no more than 500 meters (for objects located outside the city limits) ). Otherwise, the connection will be carried out according to a complicated scheme, requiring the construction of an additional substation and, possibly, the personal participation of the applicant.

After the fulfillment of the technical conditions by both parties to the contract, the specialists of the specialized electrical installation team must perform the actual connection of the object.

MOESK connection, performed through the official website of the power grid organization, looks like a very attractive undertaking, but it is not without certain difficulties. After all, its success largely depends on the actions and perseverance of the applicant himself. If you use the support of a specialized company, then all possible problems will be solved as they appear and with minimal participation of the future subscriber.

Many citizens of Moscow and the Moscow Region, faced with the need to connect objects to external power supply networks, are interested in the procedure for implementing a procedure called -. This is due to the fact that the majority of new subscribers in the Moscow region become full-fledged consumers of electricity only after they become customers of the represented company.

The accession sequence is standard, and its passage is similar for almost all new applicants. Therefore, if you do not have a lack of free time, if your element is going through the authorities and boring collection of the necessary documentation, then it is quite possible to perform such a procedure on your own. To do this, visit the company's website, find the section in it - " MOESK official website technological connection» and get acquainted with the features of the provided service. Everything else is in your hands: you can apply on the official portal of the company and independently collect the required documents.

At the same time, the owner of an electrified object always has an alternative: he can turn to the services of specialized specialists or organizations that provide comprehensive support in organizing such work. This will not greatly affect the contents of your wallet, but it will save time and allow you to achieve the final goal without ever visiting the representative office of the electric grid company.

But let's get back to the first way of going through the connection procedure, because today not all potential consumers of electricity are aware of it.

Procedure for submitting an application via the Internet

First of all, the owner of the connected object must register on the website of the network company. Then they are served application for technological connection MOESK. Scanned documents from the following list must be attached to the application:

  • passport scan;
  • a scan of the certificate confirming the right of ownership;
  • an electronic copy of the certificate of compulsory pension insurance.

If electricity supply object implies the simultaneous connection and increase in allocated power, then the applicant is obliged to attach copies of documents confirming the amount of current power. As a rule, these documents are accompanied by acts of delimitation drawn up during the previous connection.

Electronic copies of documents are uploaded to the network company's website, after which the user who submitted the application can count on its consideration in the very near future.

Within the first week from the date of registration of the application, representatives of the power grid organization must provide the applicant with an electronic contract for connecting the facility to the power supply networks. are provided to the future subscriber together with the contract.

Before starting the connection procedure, the customer must make sure that the connected object is no more than 300 meters away from the centralized networks (for objects located within the city limits) and no more than 500 meters (for objects located outside the city limits) ). Otherwise, the connection will be carried out according to a complicated scheme, requiring the construction of an additional substation and, possibly, the personal participation of the applicant.

After the fulfillment of the technical conditions by both parties to the contract, the specialists of the specialized electrical installation team must perform the actual connection of the object.

MOESK connection, performed through the official website of the power grid organization, looks like a very attractive undertaking, but it is not without certain difficulties. After all, its success largely depends on the actions and perseverance of the applicant himself. If you use the support of a specialized company, then all possible problems will be solved as they appear and with minimal participation of the future subscriber.

1. Submission of an application for technological connection to electric networks to an electric grid organization.

We submit and track an application to the network organization:

application forms of JSC OEC and PJSC MOESK Format
JSC OEK up to 150 kW inclusive docx download
JSC OEK for temporary technological connection docx download
JSC OEK for power re-registration docx download
JSC OEK redistribution of electric power docx download
JSC OEC over 150 kW docx download
JSC OEC of an individual up to 15 kW inclusive docx download
PJSC MOESK up to 150 kW inclusive doc download
PJSC MOESK for temporary technological connection doc download
PJSC MOESK for connection of power receiving devices doc download
PJSC MOESK individual up to 15 kW doc download
PJSC MOESK of an individual to receive redistributed capacity doc download
  • for technological connection ("new" technological connection to electric networks)
  • to increase the existing electrical capacity of the facility
  • redistribution or re-registration of electric power
  • temporary technological connection

Documents attached to the application:

  • plan for the location of power receiving devices;
  • one-line diagram of the applicant's electrical networks (if necessary, depending on the voltage level);
  • power of attorney or other documents confirming the authority of the representative.
  • title documents
  • documents for ownership or rent (from 1 year)

When deciding which power grid organization to apply for technological connection to, attention should be paid to the distance from the boundaries of the applicant's site to the nearby power grid facilities of the grid organization.

2. Conclusion of an agreement for technological connection and obtaining technical conditions

Within 30 days from the date of receipt of the application, the Grid Organization sends to the applicant for signing a completed and signed draft agreement in 2 copies and technical specifications as an integral annex to the agreement.

The applicant signs both copies of the draft agreement within 30 days from the date of receipt of the draft agreement signed by the network organization and sends 1 copy of the network organization with documents confirming the authority of the person who signed such an agreement.

In case of disagreement with the draft contract submitted by the grid organization and (or) its non-compliance with the Rules for Technological Connection, the applicant has the right to send the grid organization a reasoned refusal to sign the draft contract with a proposal to change the submitted draft contract and a requirement to bring it into line with the Rules for Technological Connection.

3. Design

The design process includes:

  • calculation of possible loads on the electrical network;
  • the route of the power supply system and its design;
  • protective switching equipment;
  • final stage: approval of the project or single-line diagram.

4. Fulfillment of Technical Conditions

The technical conditions contain a list of activities that must be performed both by the grid organization and by the customer.

Fulfillment of technical conditions is carried out jointly by the grid company and the applicant. The TU contains columns for “obligations of the applicant” and “obligations of the grid company”. In particular cases, the fulfillment of technical specifications is almost completely carried out by one of the parties, which is prescribed in the technical specifications.

5. Electrical work

We offer comprehensive services for the installation of electrical networks and power equipment.

All types of electrical installation:

  • construction, repair and replacement of power equipment
  • CL laying - 0.4 kV
  • installation of metering units at the border of the section of the balance sheet;
  • installation work of internal power supply using modern technologies;
  • commissioning works.

6. Obtaining certificates of admission

If all work has been carried out in accordance with the specifications, you must obtain:

  • Act on the implementation of technological connection;

  • Act of delimitation of balance sheet ownership and Act of operational responsibility;

  • technical report from the electrical laboratory (if necessary);
  • Certificate of admission of the electrical installation into operation (if necessary);
  • Certificate of admission of electrical energy metering devices (sealing of the unit (s) of electrical energy metering).

7. Conclusion of an energy supply agreement with an energy retail company

The final stage of connection to electric networks after passing through all the stages and obtaining all the necessary documentation by turning on the switching device by the electric grid company, the actual supply of electricity to the consumer's electrical installation is carried out.

Documents to be submitted for concluding an energy supply contract:

  • Application for concluding an energy supply contract
  • Certificate of state registration of a legal entity / individual entrepreneur.
  • Certificate of registration with the tax authority at the location in the Russian Federation.
  • A document confirming the authority of the applicant (representative of the applicant) to conclude the Agreement (power of attorney / extract from the protocol (decision, order) / copy of the passport (for an individual entrepreneur)).
  • Documents confirming the right of ownership or other legal grounds for owning power receiving devices (certificate of state registration of the right to an object, lease agreement, court decision, etc.) or documents confirming the right to own and (or) use a land plot.
  • Act on technological connection and / or act of delimitation of the balance sheet ownership of power networks.
  • The certificate of admission of the metering device into operation or another document on the admission to operation of the metering device (if the applicant has a metering device).
  • The act of approval of technological and / or emergency armor (if the applicant has it).

Decree of the Government of the Russian Federation No. 95 dated February 10, 2014 amended the regulatory legal acts regulating the procedure for the sale of electrical energy in retail markets. According to these changes, it is allowed to conclude contracts for energy supply (purchase and sale (supply) of electric energy (capacity)) in relation to consumer facilities (power receiving devices) even before the completion of the procedure for their technological connection to the networks of a grid organization. However, power supply will start only after the signing of the technological connection act.

Liked the article? Share with friends!
Was this article helpful?
Yes
Not
Thanks for your feedback!
Something went wrong and your vote was not counted.
Thank you. Your message has been sent
Did you find an error in the text?
Select it, click Ctrl+Enter and we'll fix it!